Reference.

Zauner Anlagentechnik

ALZ-Pfaffenau, Nemačka: Izrada i montaža cevovoda za tehnološku vodu i naftu.

2012

Zauner Anlagentechnik

Izrada i montaža cevovoda za NTT(sušenje na niskim temperaturama) Tulln, Austrija

2012

NIS-Oil Refinery Pančevo

Izrada i montaža čelične cevne instalacije, mašinsko montažni radovi na ugradnji priključaka u bloku 5 i 6, izvođenje mašinskih radova, dreniranje kanala

2012

Lenzing AG, Austrija

Izrada 14 rezervoara

2012

HAW Linings

Prefabrikacija cevovoda

2012

Danieli

Izrada metalnih konstrukcija i poteznog cilindara

2012

Integral Montage GmbH, Srbija gas, Novi Sad

Izgradnja i montaža podzemnog skladišta gasa i pripadajućeg cevovoda

2012

Integral Anlagentechnik GmbH, Germany

Izrada i montaža cevovoda za termoelektrenu GDK Mellach, Austria

2010-2011

NIS OlL REFINERY Pančevo, Serbia

DEMI Water plant

2014

NIS OlL REFINERY Pančevo, Serbia

DEMI Water plant

2014

NIS OlL REFINERY Pančevo, Serbia

Condensate polishing plant

2013-2014

NIS OlL REFINERY Pančevo, Serbia

Closed drainage system in blocks 5 and 6

2013-2014

NIS OlL REFINERY Pančevo, Serbia

“Renovation of Soot Blowers at the Energy Plant Boilers”

2013-2014

ZAUNER Anlagentechnik GmbH

Prefabrication pipes and erection pipes project Arsenal Vienne

2013-2014

NIS OlL REFINERY Pančevo, Serbia

Noise reduction barriers

2013

NIS OlL REFINERY Pančevo, Serbia

Reconstruction of reservoirs FB-801 and FB-802

2013

NIS OlL REFINERY Pančevo, Serbia

Reconstruction of reservoirs for biodiesel

2013

Bertsch Energy

Prefabrication of the pipelines, project WRK‐Eren Corlu, Turkey

2013

Integral

Manufacturing of 150t of secondary supports

2013

NIS OlL REFINERY Pančevo, Serbia

Steel structure for safe unloading of trains and mobile equipment by operators

2013

NIS OlL REFINERY Pančevo, Serbia

ISBL Piping erection, pressure test, reinstatement, Commissioning and start-up assistance

2011-2013

Hutni Montage, Czech Republic

Recove boiler, Uruguay

2012-2013

NIS OlL REFINERY Pančevo, Serbia

HEURTEY PETROCHEM; France; Piping erection, pressure test, reinstatement

2012

NIS OlL REFINERY Pančevo, Serbia

Deneza M, Belgrade: Mechanical and Civil Works, Design and installation of pipelines

2012

NIS OlL REFINERY Pančevo, Serbia

Prefabrication and assembling works of the pipelines and their connections – Sampling Unit Blocks 5 and 6

2012

DANIELI, Italia

Manufacturing of the metal structures and pin puller

2012

Zauner Anlagetechnik

NTT (Niedertemperaturtrocknung) Tulln

2012

NIS OlL REFINERY Pančevo, Serbia

Construction and mechanical engineering of the drainage canals in block 5 and 6

2012

Elixir – Zorka

Project development, fabrication and erection of equipment cyclones hoopers metal constructions and pipeline, for Elixir Food Additives, approximately 500t

2012-2013

Lenzing, Austria

Manufacturing of 14 tanks stainless and carbon steel 75m3 each, diameter up to 4200mm

2012-2013

INTEGRAL MONTAGE ANLAGEN UND ROHRTECHNIK, Austria

Project: Preparation and erection of the pipelines and their supporting structures, Thyssen Krupp steel Europe, Duisburg, Bruckhausen

2012

Zauner Anlagetechnik

Manufacture and installation of piping systems for process water and diesel oil, ALZ PFAFFENAU

2012-

NIS OlL REFINERY Pančevo, Serbia

HEURTEY PETROCHEM; France: Erection of Steam – Methane Reformer for HGU Unit

2011-2012

NIS OlL REFINERY Pančevo, Serbia

Project: ISBL/ OSBL Piping prefabrication, cca 4.000 tons

2011-2012

INTEGRAL ANLAGENTECHNIK, Germany

Project: Fabrication and erection of pipeline and support construction, erection of turbine, facilities and equipment for plant Trianel Kohlekraftwerk, Liinen

2010-2011

INTEGRAL MONTAGE ANLAGEN UND ROHRTECHNIK, JP Energotehnika Južna Bačka / Srbija gas, Novi Sad

Project: Capacity extending of compressor station for injection of natural gas into underground gas storage Banatski Dvor

2010

INTEGRAL MONTAGE ANLAGEN UND ROHRTECHNIK, JP Energotehnika Južna Bačka / Srbija gas, Novi Sad

Project: lnstallation of additional power supply in underground gas storage "BanatskiDvor"

2010

CHRISTOF GROUP Austria

Works: Optimization of gas supply system in Hurezani Corbu area in Romania

2010

INTEGRAL MONTAGE ANLAGEN UND ROHRTECHNIK / SIEMENS

Project: Fabrication, delivery and erection of pipe lines for Power plant GDK Mellach, AUSTRIA

2010

INTEGRAL MONTAGE ANLAGEN UND ROHRTECHNIK, Austria

Works: Dismantling and assembling of new boiler and connecting pipeline, erection of pre heaters, ECO etc in power plant Werk-Simeringer Haide, Wien

2010

INTEGRAL MONTAGE ANLAGEN UND ROHRTECHNIK / Srbija gas, Novi Sad

Project: Fabrication, delivery and erection of underground gas storage and connecting pipe lines

2009-2010

INTEGRAL ANLAGENTECHNIK for EBS Kraftwerksanlage Germany

Works: Preparation, fabrication, delivery and erection of pipelines and support steel construction for lndustriepark Hochst

2008-2010

CHRISTOF GROUP, Austria

Works: lnstallation of project FCC-Posttreater - Petrom Refinery, Petrobrazi, Romania

2009

U.S. STEEL SERBIA, Smederevo

Project: Delivery and installation of pipe bridge; lnstallation of pipelines and pumpstations for all 4 lines of agglomeration. Reconstruction of the clean and dirty waterlines where required.

2008-2009

U.S. STEEL SERBIA, Smederevo

Works: mounting hood and piping system of the first section of a bag filter in Steel Mill, for all three converters

2008-2009

INTEGRAL MONTAGE ANLAGEN UND ROHRTECHNIK, for VOEST ALPINE Linz, Austria

Works: Preparation, fabrication, delivery and erection of boiler and connecting pipelines Block 7

2008-2009

U.S. STEEL SERBIA, Smederevo

Project: Fabrication, delivery and erection of canals and hoods on the main steel structure for the bag filter system in Steel Mill, over 950 tons

2008-2009

U.S. STEEL SERBIA, Smederevo

Project: Design and installation of steel structure. lnstallation of filter presses for mud

2008

PMT Austria

Works: Making of cyclones, canals and pipelines for the Lafarge cement plant in Hogiz.

2008

INTEGRAL ANLAGENTECHNIK for OMV Refining, Burghausen Germany

Works: Delivery and installation of pipeline and support construction

2007-2008

KREMSMTULLER INDUSTRIEAN LAGENBAU, Austria

Works: Prefabrication and erection of pipelines for power plant Energie AG Oberosterrich AH K Timelkam

2007-2008

U.S. STEET SERBIA, Smederevo and Sabac

Turn key project: Engineering, planning, manufacturing, supplying, installation and commissioning of detection and fire protection systems in US SteelSmederevo and Beli Limovi Sabac, where the works included fabrication of water tanks and new pump station

2007-2008

INTEGRAL MONTAGE ANLAGEN UND ROHRTEChNIK, for Wienstrom SIMMERING

Works: Preparation and installation of pipeline, equipment and support construction

2007-2008

U.S. STEEL SERBIA, Smederevo

Project: Revamping Pickling line #1 in Cold rolling mill, after 15 years of not working. Line was not in operation in a period of 15 years. Hydraulic system with 5 oil sub stations with pumps, pneumatic system complete, watel air supply systems, air dryers, scrubber, fan, EMG stations 5 pieces, entry, exit conveyors, step conveyors, un-coiler and tension reel, powered and deflector rolls, looped gates, looped drive car, reservoirs, pumps. Ventilation of entry and exit electrical room, motor ventilation system.

2007-2008

PMT, Austria

Works: Production and delivery of steel supporting structure for the repair of the filter plant in Cement factory Lafarge, Beočn (platform, podests ...)

2007-2008

UNISTAI, Romania

Works: Manufacturing, supply and erection of pipelines for OMV Ref inery Modernization Project

2007

U.S. STEEL SERBIA, Smederevo

Project: Delivery and installation of canals to cast iron Furnaces # 2 during the overhaul in 2007

2007

U.S. STEEL SERBIA, Smederevo

Project: Delivery and installation of electrical and control equipment and measuring instruments during the overhaulof Blast Furnace # 2

2007

U.S. STEEL SERBIA, Smederevo

Project: Delivery and installation of impulse lines during the overhaul of Blast Furnaces # 2

2007

U.S. STEEL SERBIA, Smederevo

Works: Manufacturing and installation of new f lair stack for burning of Blast Furnace gas - cca 250t of steel structure

2007

U.S. STEEL SERBIA, Smederevo

Project: Manufacturing and installation of new steel structure in Cold rolling mill, Pickling line #2 with dismantling of old 1steel structure, old equipment relocation and installation of new equipment of tension leveler delivered by VAI Clesim, France in 2006- cca 360 tons

2007

Cement factory LAFARGE, Beočn, Serbia

Works: Dismantling and installation of new filter system for cement factory, line #4 2006/2007 - cca 300 tons

2007

INTEGRAL MONTAGE ANLAGEN UND ROHRTECHNIK, Austria

Works: Preparation and erection of pipeline and its support construction for plants in waste burning factory

2006-2007

PMT, Austria

Works: Production of steel structures for the overhaul of the filtration plant Lafarge Beočin (base, stairs, platforms)

2006-2007

ESC, Germany / Dijamant, Zrenjanin, Serbia

Works: Fabrication, delivery and instaIlation of Bag filters

2006

ZAUNERGROUP Austria

Works: Fabrication and delivery of structural steel containers for bio-diesel

2005

CHELLCHAM AB Ostblocket 5-10062 Stockholm

Installation of Chlorine Plant: HD-, MD-, ND- Pipeline System (steam, condense, process water (chemicals, etc..) pipe bridges, steel structures, stages, platforms, ladders, staircases, pipe support, etc... Materials used: C-steel, warm, high temperature – strong steel, titanium, lnolloy, Hastelloy, austentic steel, synthetic and bindinq materials, casting, stainless rnetal, partly internal lining with PTFE and enamel for Chemische Werke Bitterfeld, Germany

2004-2005

CHEMIE Linz AG, Linz, Austria

Works for the chemical – and fertilizer indust: Process piping up to DN 2000, - The entire pipeline of multi (double coat, PTFE and enameled Edition) steel construction, pipe racks, platforms. Materials used: C-steel, heat resistant steel, titanium, pure silver

2004-2005

EVN NO AG Maria Enzersdorf

Works for power plants: Measurement units , Slide stations, l-lD-, MD-, ND- pipeline systems. Materials used: C-steel, plant: Korneuburg, Theiss, Deutsch-Wagram, Krems / N0 Baden, Stockerau, Wr. Neustadt

2004-2005

EVN NO AG Maria Enzersdorf

MD - ducts for condense piping systems and systems under pressure. Materials used: C-steel, heat resistant steel, austentic steel: Simmering-Graz-Pauke4 Vienna, Kohlenscheidungs - GmbH, Vienna, MAN AG, Vienna

2004

VOEST ALPINE-MONTAGE, Linz, Austria

Works for melamine plant: HD-, MD- and ND- piping systems (steam, condense, chemicals, process media, etc..) piping and general steel construction.
Materials used: heat resistant steel, Titan, low alloy, Hastelloy, authentic steel, synthetics, for the plant: Pulawy, Poland

2005

INTEGRAL MONTAGE ANLAGEN UND ROHRTECHNlK, Austria

Project: WSO4 - Fabrication and delivery canals for the flue gasses and pressure lines

2005

ZAUNERGROUP, Austria

Works: Fabrication and delivery of various types of steel structures

2005

DONAU CHEMIE AG, Vienna, Austria

Works on systems for chemical products, agro colour, production of plaster boards etc: Latex - plant piping, steam-supply, condense, hot water turbines, piping - steam heating, double coating sulfur separation and station, pipe bridges. Materials used: C-steel, heat resistant steel, austentic steel, nonferrous metal.

2004-2005

INTEGRAL MONTAGE ANLAGEN UND ROHRTECHNlK, Austria

Works on piping systems and steel structures: Piping systems for HD, MD, ND, couple, condense, hot and cold water; chemicals, high-pressure etc. Production and erection of steel structures, pipe bridges. Materials used: C-steel, steel to resist heat and high heat, Titan, lncolloy, Hastelloy, austentic steel, non-ferrous metals, partial inner lining (PTFE, enamel) for Plants: Gaswerk Simmering, Gaswerk Leopoldali, Voest Linz, Chemie Linz, Leykam-Murztaler; Bruck.

2004-2005

VOEST ALPINE INDUSTRI EANLAGENBAU, Linz, Austria

Project: Sinter Corus and Project Sinter 5 - fabrication and delive of steel piping components and parts

2004

HAINDETPAPIER PAPIERMASCIHINE / Duisburg, TOTAL RAFFINERIE / Vlissingen, HOGHST PESTIZIEDE / HURTH / KOLN, PCD PP III

Works: Deliver and performance of ISA /electro, analysis and pneumatics works

2004

PCD HOPE - Anlage und Offsite / Schwechat, LAAKIRChEN PAPIERMASCIHINE, OVV Kep-Anlage / Schwechat, Chemie Linz Dungemittel / Schwechat LEYKAM MURZTALER ROLTENTRANSPORT BRUCK/Mur

Works: Delivery and performance of ISA /electro, analysis and pneumatics works, supervision and planning

2004

VOEST ALPINE-MONTAGE, Linz, Austria

HD-, MD- and ND- piping systems (steam, condense, hot water boiling waten process water chemicals, high pressure etc.). Materials used: heat resistant steel, titanium, Hastelloy, austenitic steel, synthetic-and binding materials, casting, non-ferrous metalworks

2005

ZAUNERGROUP, Austria

Works: Fabrication and delivery of steel structure - Carinox Belgium

2004-2005

ZAUNERGROUP, Austria

Works: Fabrication and delivery of steel constructions for Staircases Donawitz

VOEST ALPINE-MONTAGE, Linz, Austria

Works: lnstallation of pipelines – Foster Wheeler ltaliana S.P.A - Project, Chemieanlage EXXON Rotterdam duplomat pipeline laying

2003

WIENERBERGER, PARMOOSER, KAOLIN.WERK, OSTERREICIH UNILEVER, KREMS CtHEMIE, MEINL, JACOBS, BENSDORF

Works: HD-, MD-, ND- piping systems for all media, steel construction, pipe bridges, torches (candles for burning excess gas)

2003

VOEST ALPINE-MONTAGE, Linz, Austria

Works for raw industry, heavy industry and metallurgical indust: HD-, steam and condense piping systems for blast furnaces, MD-ND- piping systems for steam, condense, hot water oil Hydraulic pipeline, reducer for high-pressure, supply and draſtof electricity, electricity reduce steel structure. Materials used: heat resistant C-steel, austenitic steel, non-ferrous metals, low alloy steel, casting

2003

HAINDEL PAPIER DUISBURG, LAAKIRCHEN PAPIER, LEYKAM MURZTALER, PAPIER BRUCK/MUR, STEYREMUHL PAPIER

Paper and pulp: Delivery and construction: l-lD-, MD-, ND- pipelines, steam, condense, chemicals, cellulose, water; sewel air pipes, etc.., pipeline installation of machine for paper, steel tubular construction and bridges. Materials used: C-steel, heat resistant steel, austenitic steel, synthetic materials.

2003

PCD SCHWECHAT; OMV SCHWECHAT; CIHEMIE LINZ; CHEMIE KREMS; GLANZSTOFF ST.POLTEN.

Works in refineries and chemical industries: DeIivery and installation: MD-, ND- pipeline systems, flares. Production of steel structures, pipe bridges etc

2003

THYSSEN-STAHI AG Duisburg

Delivery and construction diverse revitalization of plants. zSuction, wastewater treatment plants, HD-steam pipes, instalation of drain ducts for gas coolen. Materials used: C-steel, steel austenitic, L.4571

2003

STANDARD KESSE L.TOLKEWIT Z / DRESDEN STANDARDKESSEL DUISBURG

Production and delivery of ND –MD- condense pipelines and pipeline installation in steam boilers; MateriaIs used: C-steel, heat resistant steel austenitic stainless steel and non-ferous metals.

2003

VOEST ALPINE-MONTAGE, Linz, Austria

Production and delivery of MSR/electroworks: Plants: Minol Tanklager Perleberg, Minol Tanklager Potsdam, Hafen Rostock

2003

VOEST ALPINE-MONTAGE, Linz, Austria

Works for refineries and chemical industry: HD, MD and ND pipeline systems, steam, condense, hot water process water for Plants: Magnesitwerk Aken, DDR Production of different structures, pipelines, vessels, preparation - prefabrication pipeline systems for various Voest Alpine plants at home and abroad.

2003-2004

VOEST ALPINE-MONTAGE, Linz, Austria

Works for etilenoks-plant. HD, MD and ND pipelines (steam, condense, hot water, processed water); Steel works, under ground pipeline - for plant Chemisches Werk buna, DDR

2003